Construction of the 400 kV Ostrołęka – Olsztyn Mątki power line

narew-lomza-ostroleka-m120-1

The subject of the contract was the assembly and erection of lattice poles of a double-circuit 400 kV overhead power line between the Olsztyn Mątki substation and the Olsztyn substation.

The order included the assembly of lattice columns with a total weight of 500 tons.