In the period from 2017 to 2019, we completed comprehensive works related to the implementation of the investment under the name: “Construction of the 400 kV Gdańsk Przyjaźń – Żydowo Kierzkowo double-circuit line”.
The work consisted of:
– assembly and erection of poles with a total weight of 3,345 tons;
– installation of phase conductors, bridges and spacers with accessories – 2x3x3xAFL –8350mm2 – 2x3x3x 26.399 km;
– OPGW cables installation – 2 x 23.966 km.