Construction of the 400 kV double-circuit overhead power line Ełk – the border of the Republic of Poland

400kV-Ełk-GranicaRP-derrick copy

The subject of the contract was the assembly and erection of lattice poles of a double-circuit 400 kV overhead power line between the Ełk Bis substation and the border of the Republic of Poland. The line is equipped with 2 lightning conductors associated with OPGW optical fibers.

The order included the assembly of 1,408 tons of lattice power poles.

Completion date: 2014-2015